Communication From Jim Corley: Paving Notice - Route 164

Document

Route 164 Milling and Resurfacing Project

The State of Connecticut has scheduled a milling and resurfacing project for Route 164 from Route 2 in Preston to Route 138 in Griswold starting on June 10, 2022. 

  • The tentative start date for the MILLING portion of this project is scheduled to begin on Friday, June 10, 2022, and continue for approximately three (3) weeks ending on Wednesday, June 29, 2022.
  • The tentative start date for the PAVING portion of this project is scheduled to begin on Monday, July 18, 2022 and continue for approximately three (3) weeks ending on Friday, August 5, 2022. 

~For both portions of this project the work hours will be from 7:00 a.m. through 5:00 p.m. each day.~

*NOTE:  Adjustments to this schedule may be necessary due to inclement weather.